Postby Sud Fri Jul 11, 2014 11:46 am

You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process?

A. Distribute Information

B. Plan Communications

C. Report Performance

D. Manage Project Team

My Answer-D
Scordo. What should be right answer? As per me, PM is managing the team by having them record the time.

--Sud
pankaj.barnwal
Beginner
Beginner
Posts: 42
Joined: Fri May 30, 2014 5:05 am

Re: Question for Discussion-Team

Postby pankaj.barnwal Fri Jul 11, 2014 11:53 am

My answer:
B. Plan Communications

Because, this is not happening at execution time, rather project manager planned that team members record their time. So, it should be planning part.
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Question for Discussion-Team

Postby namita Fri Jul 11, 2014 12:41 pm

This is a old question. distribute information was part of PMBOK4. Ignore this and if you want to understand the difference between PMBOK 4 & 5 around this, go through below blog

http://www.izenbridge.com/blog/communic ... furcation/
yogesh
Contributor
Contributor
Posts: 142
Joined: Sat Apr 19, 2014 10:44 am

Re: Question for Discussion-Team

Postby yogesh Fri Jul 11, 2014 12:49 pm

its shd be Answer D

team will be recording during Execution as part of Work performance data .Manage team is in Execution process group

Return to “PMP® Open Forum”