Procurement

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
Satya
Posts: 15
Joined: Mon Oct 29, 2018 1:17 am

Procurement

Postby Satya Mon Oct 29, 2018 7:10 pm

Context is :
The organization has a good relation with sole source vendor but even after many request he is delivering a bad quality which is not meeting the client requirements .project is about to get cancel. what should a PM do..?
manishpn
Expert
Expert
Posts: 2588
Joined: Sat Jan 04, 2014 3:55 pm

Re: Procurement

Postby manishpn Sun Nov 25, 2018 6:48 pm

Satya wrote:Context is :
The organization has a good relation with sole source vendor but even after many request he is delivering a bad quality which is not meeting the client requirements .project is about to get cancel. what should a PM do..?


Sorry post the exact question,
if the vendor is sole, there is not much PM can do expect take the steps mentioned in contract if the vendor is breaching the contract, legally it is called as remedial actions/rights
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
PCS
Posts: 19
Joined: Thu Oct 25, 2018 8:50 am

Re: Procurement

Postby PCS Thu Nov 29, 2018 6:51 am

Organization has a good relation with sole source vendor - Your Role is Buyer
not meeting the client requirements/Project about to Cancel - Your Role is Seller
So, i presume in this context its given for sub-contracting.
This is a tricky situation where yourself is in a legal obligation to customer/client. Answers can be subjective based on schedule effected, going quickly for pre-qualified sellers, initiating claims wrt to quality requirements etc. If any options given would have made this easier.