Change to the Project Management Plan via Change Request

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
salman_2005
Participant
Participant
Posts: 58
Joined: Wed Sep 26, 2018 8:15 pm

Change to the Project Management Plan via Change Request

Postby salman_2005 Tue Oct 16, 2018 5:31 am

Hello Manish and other experts,

It is mentioned in PMBOK that "Any change to the Project Management Plan goes through the org's change control process via a change request".

This means that any change to Scope Management Plan or Resource Management Plan etc. (Without impacting any baseline) can be done through the change request mode only.

I was in the impression that when a baseline gets impacted only then we raise a CR else PM can update the project management plan.

Please help in understanding.

Thank you.

Salman
manishpn
Expert
Expert
Posts: 2577
Joined: Sat Jan 04, 2014 3:55 pm

Re: Change to the Project Management Plan via Change Request

Postby manishpn Tue Oct 16, 2018 4:03 pm

salman_2005 wrote:Hello Manish and other experts,

It is mentioned in PMBOK that "Any change to the Project Management Plan goes through the org's change control process via a change request".

This means that any change to Scope Management Plan or Resource Management Plan etc. (Without impacting any baseline) can be done through the change request mode only.

I was in the impression that when a baseline gets impacted only then we raise a CR else PM can update the project management plan.

Please help in understanding.

Thank you.

Salman


[b] it depends on the change management plan of the project, for smaller changes it need not go through CCB , this statement says that change control process has to be followed so a formal CR is needed but not all CRS go to CCB for approval.
[/b]
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
salman_2005
Participant
Participant
Posts: 58
Joined: Wed Sep 26, 2018 8:15 pm

Re: Change to the Project Management Plan via Change Request

Postby salman_2005 Tue Oct 16, 2018 4:54 pm

So, if a CR is created which is not meant to go to the CCB. Then, who would approve this CR? Project Manager or any other person as mentioned in the change management plan?

All CRs do not go to CCB, so the perform integrated change control process would not be followed for all the CRs. Which means for eg. a CR can be raised and dealt by the PM? Where this CR would go if it is not going to the CCB or perform integrated change control process?

Please clarify

Thank you.

Salman
manishpn
Expert
Expert
Posts: 2577
Joined: Sat Jan 04, 2014 3:55 pm

Re: Change to the Project Management Plan via Change Request

Postby manishpn Wed Oct 17, 2018 9:54 am

salman_2005 wrote:So, if a CR is created which is not meant to go to the CCB. Then, who would approve this CR? Project Manager or any other person as mentioned in the change management plan?
It is mentioned in the project (Change) management plan, it depends on size, complexity, goegraphical presense etc.
for e..g for 5 Million dollar project, you need not go to CCB for a few thousand worth CR approval, or for 2 year duraiton project CCB need not approve a 1 day worht change
also if project is run in different countries, sometimes the country SPOC has some authority to approve CRs upto certain level.


All CRs do not go to CCB, so the perform integrated change control process would not be followed for all the CRs. Which means for eg. a CR can be raised and dealt by the PM? Where this CR would go if it is not going to the CCB or perform integrated change control process?
ALL CRs have to formally logged in Change LOG, if PM has authority to approve, then it will be mentioned in change log that PM has approved with reason, comments etc.


Please clarify

Thank you.

Salman
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
salman_2005
Participant
Participant
Posts: 58
Joined: Wed Sep 26, 2018 8:15 pm

Re: Change to the Project Management Plan via Change Request

Postby salman_2005 Wed Oct 17, 2018 6:43 pm

Thanks a ton Manish! Very helpful.

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 15 guests