Cost of non conformance - External failure cost

Postby salman_2005 Thu Oct 11, 2018 8:55 am

Is cost of non conformance - external failure cost is the part of project budget or is it a part of operation and maintenance?

Please help in understanding.

Thanks

Salman
manishpn
Expert
Expert
Posts: 2588
Joined: Sat Jan 04, 2014 3:55 pm

Re: Cost of non conformance - External failure cost

Postby manishpn Tue Oct 16, 2018 3:56 pm

salman_2005 wrote:Is cost of non conformance - external failure cost is the part of project budget or is it a part of operation and maintenance?

Please help in understanding.

Thanks

Salman


if non conformance is detected within project duration the cost is on Project , if its detected after the handover to production or whoever is receiver and project is close the cost is taken by operations
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
salman_2005
Participant
Participant
Posts: 58
Joined: Wed Sep 26, 2018 8:15 pm

Re: Cost of non conformance - External failure cost

Postby salman_2005 Tue Oct 16, 2018 4:41 pm

Thank you Manish!