Postby salman_2005 Sun Oct 07, 2018 4:27 am

Hi Manish,
Is Approved Change request an input to Control Scope process as well? Though, PMBOK doesn't mention it in the input.

Is it like if the change is approved in the scope then the scope baseline would get updated through the control scope process?

Please help in understanding.

Thanks
Salman
manishpn
Expert
Expert
Posts: 2577
Joined: Sat Jan 04, 2014 3:55 pm

Re: Approved Change Requests

Postby manishpn Tue Oct 09, 2018 9:00 pm

salman_2005 wrote:Hi Manish,
Is Approved Change request an input to Control Scope process as well? Though, PMBOK doesn't mention it in the input.

Is it like if the change is approved in the scope then the scope baseline would get updated through the control scope process?

Please help in understanding.

Your understanding is right when a CR is approved which impacts the scope then scope baseline is revised and control scope process refers to latest version of the scope baseline,

Thanks
Salman
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
salman_2005
Participant
Participant
Posts: 58
Joined: Wed Sep 26, 2018 8:15 pm

Re: Approved Change Requests

Postby salman_2005 Wed Oct 10, 2018 7:24 pm

Thank you Manish!

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 14 guests