As per my Understanding and referring to the videos the Quality Management Plan is the part of the Project Management Plan which is input to Scope Management Plan
Kindly clarify the below Quaetion

Question 22

1.00/0.00


Jay and his team have just begun planning phase for their project which has the duration of 3 years. The team has gone through project charter and is now developing scope management plan. One of the team members comes to Jay and mentions that project Management plan does not have quality management plan and this is posing challenge. Jay is not sure if quality management plan is a critical input for developing Scope management plan. What may be true from the following in the given scenario?

♣Project Management Plan is not required at this stage
♣Team member may not be referring to correct version of project management plan
♣Quality Management plan is independent plan and not part of project management plan
♣Project management plan will not have all subsidiaries at this stage
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Scope Management

Postby manishpn Mon Aug 13, 2018 7:33 pm

not sure what is the query?

did you read the explanation provided?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
BhanotN
Posts: 6
Joined: Tue Aug 07, 2018 4:37 pm

Re: Scope Management

Postby BhanotN Tue Aug 14, 2018 6:50 pm

Hello Manish My query is that as per the Videos and as per my understanding Quality Management is the part of Project Management Plan which is the input of the Scope Management Plan (Planning)

And the Explanation in the answer states that PMP donot have all the subsidiary Plans at this time

Kindly clarify the same
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Scope Management

Postby manishpn Tue Aug 14, 2018 7:21 pm

the idea behind the question it to tell students that Project management plan is built iteratively, so not all subsidiaries are in initial versions of PMP
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
BhanotN
Posts: 6
Joined: Tue Aug 07, 2018 4:37 pm

Re: Scope Management

Postby BhanotN Mon Aug 20, 2018 7:02 pm

Hello Manish,
Still not Clear,
I understand that the Other Plans are iterative .
But since it is the Part of the Quality Management is the part of Project Management Plan which is the input of the Scope Management Plan (Planning)
Can you explain if this is the Correct Choice of answer
Because the answer is confusing

Can you please clarify a bit more
Regards,
Neema
nazrulq
Contributor
Contributor
Posts: 268
Joined: Sun Feb 26, 2017 6:06 am

Re: Scope Management

Postby nazrulq Mon Sep 03, 2018 5:18 am

In my opinion Quality Management Plan is NOT well prepared at this level. Last option is the best answer, I guess!
ihuseynli
Beginner
Beginner
Posts: 25
Joined: Mon Aug 20, 2018 7:16 am
Location: Baku, Azerbaijan

Re: Scope Management

Postby ihuseynli Mon Sep 03, 2018 6:13 am

Here, Answer can be found by elimination

♣Project Management Plan is not required at this stage - WRONG
♣Team member may not be referring to correct version of project management plan
♣Quality Management plan is independent plan and not part of project management plan - WRONG
♣Project management plan will not have all subsidiaries at this stage

1 and 3 are wrong for sure. 2 and 4 is left. Yes, 2 can be true also, but 4 is real situation. I've 8 year experience in directiong projects and choise 4 is real situation in the begining stages
Br,
Ismayil Huseynli, ITIL®, OCE®, OCA®
Baku, Azerbaijan
www.linkedin.com/in/ismayilhuseynli
seema.sonkiya
Expert
Expert
Posts: 2104
Joined: Fri Jul 11, 2014 11:57 am

Re: Scope Management

Postby seema.sonkiya Wed Sep 05, 2018 5:25 am

As a iZenBridge customer, please post your questions in the exclusive area, I am moving there.