Identify Risk Query

Postby pankaj.barnwal Thu Jul 03, 2014 10:28 am

Is risk identification done in Project/Phase Closing?
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Identify Risk Query

Postby namita Thu Jul 03, 2014 11:44 am

hi Pankaj,

Why do you feel Risk Identification will be done in project/phase closure? Please elaborate so that we can understand the confusion well
yogesh
Contributor
Contributor
Posts: 142
Joined: Sat Apr 19, 2014 10:44 am

Re: Identify Risk Query

Postby yogesh Fri Jul 04, 2014 4:09 am

Risk identification is done in palnning stage.
After that we check in control stage for NEW risk.
So last its done in control stage.
pankaj.barnwal
Beginner
Beginner
Posts: 42
Joined: Fri May 30, 2014 5:05 am

Re: Identify Risk Query

Postby pankaj.barnwal Fri Jul 04, 2014 6:02 am

Procurement closure comes in Close phase.
So, it is possible that procurement closure happened, but it left some secondary risk that can lead to identify new risks?

Also, in PMPBOK it is written that risk identification is done throughout the project. So, it means that it should be done till project is officially closed?
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Identify Risk Query

Postby namita Fri Jul 04, 2014 6:18 am

Pankaj, you are right in your understanding that Risk can be identified through out the project. However think from a practical scenario. If your project/phase is a closure stage, what kind of risk you can identify and what action we can take for it as anyway we are at closure. Definitely when we shall evaluate such risks at closure stage, it should be very low priority Risk because project is already near closure. If not then yes we can't close the project and need to rework to control close that risk

Hope its clear
pankaj.barnwal
Beginner
Beginner
Posts: 42
Joined: Fri May 30, 2014 5:05 am

Re: Identify Risk Query

Postby pankaj.barnwal Fri Jul 04, 2014 7:03 am

Yes I got it.

Some low risks can be identified, but it may be possible that that risk has almost negligible effect on deliverable.

Thanks.
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Identify Risk Query

Postby namita Fri Jul 04, 2014 8:17 am

Ok, feel free to post more questions you are struggling with :)
kunwar
Posts: 10
Joined: Fri Dec 01, 2017 10:28 am

Re: Identify Risk Query

Postby kunwar Mon Jun 18, 2018 9:40 am

Is Sponsor included during Identify risk Process( Page 411 _ PMBOK 6)
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Identify Risk Query

Postby manishpn Mon Jun 18, 2018 10:05 am

there is no guideline on not to include Sponsor,

PM can and should involve all right stakeholders for risk identification
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 7 guests