Webinar on Critical Path : Q4

Postby namita Wed Jan 01, 2014 10:50 am

Look at the below N/W diagram and identify the critical path
Attachments
Q4.png
Q4.png (26.83 KiB) Viewed 788 times
Pashi
Beginner
Beginner
Posts: 40
Joined: Tue Dec 24, 2013 12:48 am

Re: Webinar on Critical Path : Q4

Postby Pashi Fri Jan 03, 2014 3:48 am

No. of possible Paths from Start to End -

ACE = 18
BDE = 13
BCE = 18

Since their are 2 routes with same highest duration,it means that a delay in any one of those tasks will cause a delay to the completion of the project. Hence both ACE and BCE are critical paths.
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Webinar on Critical Path : Q4

Postby namita Fri Jan 03, 2014 4:30 am

There is a typo in diagram, activity B is 4 days.. but answer is correct