Look at below N/W diagram and find out what is the project duration if there is a lag between activity B & C of 2 days and relationship start to start
- Attachments
-
- Q3.png (18.43 KiB) Viewed 1748 times
Re: Webinar on Critical Path: Q3
Please see attached the solution.
My answer is 15 days.
My answer is 15 days.
- Attachments
-
- Webinar on Critical Path Q3_1.jpg (17.6 KiB) Viewed 1743 times
Re: Webinar on Critical Path: Q3
Good work Pashi.. join our webinar for further discussion