Webinar on Critical Path : Q2

Postby namita Tue Dec 31, 2013 7:27 am

Look at below N/W diagram and find out what is the project duration if there is a lead between activity B & C of 3 days and relationship finish to finish
Attachments
Q2.png
Q2.png (18.29 KiB) Viewed 1800 times
Pashi
Beginner
Beginner
Posts: 40
Joined: Tue Dec 24, 2013 12:48 am

Re: Webinar on Critical Path : Q2

Postby Pashi Fri Jan 03, 2014 4:30 am

Project Duration = 11 days.
Last edited by Pashi on Fri Jan 03, 2014 4:44 am, edited 1 time in total.
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Webinar on Critical Path : Q2

Postby namita Fri Jan 03, 2014 4:32 am

Check the question again... Lead is of 3 days.. recalculate and post
Pashi
Beginner
Beginner
Posts: 40
Joined: Tue Dec 24, 2013 12:48 am

Re: Webinar on Critical Path : Q2

Postby Pashi Fri Jan 03, 2014 4:44 am

My Bad. I assumed a lead of 2 days!

Uploading the solution with right Lead.

Total project Duration is 10 Days.
Attachments
Webinar on Critical Path Q2.jpg
Webinar on Critical Path Q2.jpg (17.32 KiB) Viewed 1777 times
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Webinar on Critical Path : Q2

Postby namita Fri Jan 03, 2014 5:47 am

good work :)