Webinar on Critical Path : Q1

Postby namita Tue Dec 31, 2013 6:12 am

Look at below N/W diagram and find out what is the project duration if there is a lag between activity B & C of 3 days
Attachments
Q1.png
Q1.png (17.4 KiB) Viewed 1441 times
Pashi
Beginner
Beginner
Posts: 40
Joined: Tue Dec 24, 2013 12:48 am

Re: Webinar on Critical Path : Q1

Postby Pashi Fri Jan 03, 2014 4:38 am

Since no relationship type between activity B and C is defined, hence assuming its a FS type of relationship by default.

Based on that, the project duration is 18 Days.
Attachments
Webinar on Critical Path Q1.jpg
Webinar on Critical Path Q1.jpg (16.51 KiB) Viewed 1418 times
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Webinar on Critical Path : Q1

Postby namita Fri Jan 03, 2014 4:42 am

Yes, right ;)