Please reply

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
pruhela
Posts: 6
Joined: Wed Mar 07, 2018 5:14 am

Please reply

Postby pruhela Tue Apr 17, 2018 2:44 pm

You are the project manager of a project whose team has interacted with a number of stakeholders. You believe that in order to have an objective project performance appraisal, you would like to obtain feedback for the project team members from all the people they have worked with, including superiors, peers and subordinates. Project performance appraisals are performed during which of the following processes?

a) Develop Team
b) Close Project or Phase
c) Acquire Resources
d) Manage Team
manishpn
Expert
Expert
Posts: 2406
Joined: Sat Jan 04, 2014 3:55 pm

Re: Please reply

Postby manishpn Wed Apr 18, 2018 6:15 am

this is quiet easy, you should attempt it first and then we can discuss
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
pruhela
Posts: 6
Joined: Wed Mar 07, 2018 5:14 am

Re: Please reply

Postby pruhela Wed Apr 18, 2018 6:57 am

Thanks for your reply

but i have a confusion here..

In manage team process we have team performance assessment as an input.

In develop team process we have also team performance assessment as an output and recognition and rewards as tools and techniques.


not able to judge between manage team and develop team

Regards
manishpn
Expert
Expert
Posts: 2406
Joined: Sat Jan 04, 2014 3:55 pm

Re: Please reply

Postby manishpn Wed Apr 18, 2018 6:31 pm

pruhela wrote:Thanks for your reply

but i have a confusion here..

In manage team process we have team performance assessment as an input.

In develop team process we have also team performance assessment as an output and recognition and rewards as tools and techniques.


not able to judge between manage team and develop team

Regards


This question is based on PMBOK5
PMBOK 6 does not have project performance appraisal as a terminology

As per PMBOK6, individual and team assessment is done in develop team,
Br,
Manish P