Closing PG Query

Postby Prachi Bansal Thu Mar 15, 2018 4:46 pm

The Kelly is making sure that the product of the project has been completed according to the project management plan. What part of the project management process is she in?


Planning


Executing


Monitoring and Controlling


Closing

Correct answer should be Monitoring & controlling since, Control quality is the process where deliverables are converted into verified deliverables and in Scope Validation they are further converted into accepted deliverables. But answer given is Closing. It shouldn't be closing as In closing PG, deliverables are already accepted. Process is just closed in it.
manishpn
Expert
Expert
Posts: 2406
Joined: Sat Jan 04, 2014 3:55 pm

Re: Closing PG Query

Postby manishpn Sun Apr 15, 2018 3:36 pm

comparing actual work don against PMP is done is M and C project work

whereas in closing project or phase the PM if ALL the work is completed as part of that project or Phase
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/