Execution Process Group Question

Postby asimali Sun Mar 11, 2018 9:03 pm

Hi ,

I have answered this as option C but the answer in the mock was option D.
Please advise.

During executing, change requests are raised in the project. The project manager is implementing these changes by following the change management plan. Which parameter/s should be implemented? Choose the best answer.

A- Corrective actions
B- Preventive actions
C- Approved changes
D- Approved changes and corrective actions


Regards
Asim Ali
manishpn
Expert
Expert
Posts: 2475
Joined: Sat Jan 04, 2014 3:55 pm

Re: Execution Process Group Question

Postby manishpn Sun Apr 15, 2018 4:28 pm

asimali wrote:Hi ,

I have answered this as option C but the answer in the mock was option D.
Please advise.

During executing, change requests are raised in the project. The project manager is implementing these changes by following the change management plan. Which parameter/s should be implemented? Choose the best answer.

A- Corrective actions
B- Preventive actions
C- Approved changes
D- Approved changes and corrective actions

Both option C and D can be correct, however as PM you while implementing the approved changes you as PM are also in a way implementing corrective actions, remember, 'corrective actions taken when non-conformance have already been detected to rectify the cause of the issue.'
Regards
Asim Ali
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/