Query

Postby Prachi Bansal Sun Mar 11, 2018 12:55 am

What should be the correct answer and why?

Your project is multi phased; there has been multiple brainstorming sessions with your stakeholders to decide on which phase to phase relationship is chosen for project. There has been split of opinion with one group pushing for sequential relationship while other group is favoring overlapping relationship. Your sponsor is also inclined to go with overlapping relationship. You know that based on decision there will be impact on how your project plan will be formulated. Phase to Phase relationship decision will impact which subsidiary plan the MOST ?


Human Resource Management plan


Change Management plan


Schedule Management plan


Requirements Management plan
rabiyajamal45
Posts: 1
Joined: Sat Mar 10, 2018 9:58 am

Re: Query

Postby rabiyajamal45 Mon Mar 12, 2018 6:55 am

Good Query
manishpn
Expert
Expert
Posts: 2539
Joined: Sat Jan 04, 2014 3:55 pm

Re: Query

Postby manishpn Sun Apr 15, 2018 4:17 pm

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist