Question

Posted: Sun Mar 04, 2018 11:30 am
by brijrajpandey
When do you perform stakeholder analysis?

A. When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control

Re: Question

Posted: Mon Mar 05, 2018 9:51 pm
by manishpn
i was waiting for others to start discussion,

would you like to attempt with a reasoning so we can have good discussion

Re: Question

Posted: Tue Mar 06, 2018 4:13 am
by nagak7079@gmail.com
I will go by C

SH analysis is continuous process in planning grp.

A. When defining the project scope (no, scope defined by charter)
B.When developing the project charter (identity key SH with the help of charter)
C.When creating the project management plan ( master plan to engage all other plans,SH plan is part of it)
D.When putting changes through change control (no)

Re: Question

Posted: Sun Apr 15, 2018 4:47 pm
by manishpn
brijrajpandey wrote:When do you perform stakeholder analysis?

A. When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control


stakeholder analysis is a continuous process, it starts when Project charter is developed, matures during developing project management plan and then gets continuously done during execution of the project