Question

Postby brijrajpandey Sun Mar 04, 2018 11:30 am

When do you perform stakeholder analysis?

A. When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control
manishpn
Expert
Expert
Posts: 2467
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question

Postby manishpn Mon Mar 05, 2018 9:51 pm

i was waiting for others to start discussion,

would you like to attempt with a reasoning so we can have good discussion
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nagak7079@gmail.com
Posts: 9
Joined: Thu Mar 02, 2017 5:14 pm

Re: Question

Postby nagak7079@gmail.com Tue Mar 06, 2018 4:13 am

I will go by C

SH analysis is continuous process in planning grp.

A. When defining the project scope (no, scope defined by charter)
B.When developing the project charter (identity key SH with the help of charter)
C.When creating the project management plan ( master plan to engage all other plans,SH plan is part of it)
D.When putting changes through change control (no)
manishpn
Expert
Expert
Posts: 2467
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question

Postby manishpn Sun Apr 15, 2018 4:47 pm

brijrajpandey wrote:When do you perform stakeholder analysis?

A. When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control


stakeholder analysis is a continuous process, it starts when Project charter is developed, matures during developing project management plan and then gets continuously done during execution of the project
Br,
Manish P