Question

Postby brijrajpandey Sun Mar 04, 2018 11:30 am

When do you perform stakeholder analysis?

A. When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control
manishpn
Expert
Expert
Posts: 2590
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question

Postby manishpn Mon Mar 05, 2018 9:51 pm

i was waiting for others to start discussion,

would you like to attempt with a reasoning so we can have good discussion
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nagak7079@gmail.com
Posts: 9
Joined: Thu Mar 02, 2017 5:14 pm

Re: Question

Postby nagak7079@gmail.com Tue Mar 06, 2018 4:13 am

I will go by C

SH analysis is continuous process in planning grp.

A. When defining the project scope (no, scope defined by charter)
B.When developing the project charter (identity key SH with the help of charter)
C.When creating the project management plan ( master plan to engage all other plans,SH plan is part of it)
D.When putting changes through change control (no)
manishpn
Expert
Expert
Posts: 2590
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question

Postby manishpn Sun Apr 15, 2018 4:47 pm

brijrajpandey wrote:When do you perform stakeholder analysis?

A. When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control


stakeholder analysis is a continuous process, it starts when Project charter is developed, matures during developing project management plan and then gets continuously done during execution of the project
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
ihuseynli
Beginner
Beginner
Posts: 49
Joined: Mon Aug 20, 2018 7:16 am
Location: Baku, Azerbaijan

Re: Question

Postby ihuseynli Sat Aug 25, 2018 9:45 am

Hi manishpn, I couldn't catch your answer. You explain about SH analysis as continuous process. But ther is no appropriate answer here. My logic:
- SH analysis is a technique used in Identify SH process
- Identify SH process is in Initiation PG
- In project charter you also put little info about stakeholders
- So, for me answer becomes 'B' . First time when you analyise SH

What do you think about it?
Br,
Ismayil Huseynli, ITIL®, OCE®, OCA®
Baku, Azerbaijan
www.linkedin.com/in/ismayilhuseynli
manishpn
Expert
Expert
Posts: 2590
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question

Postby manishpn Sat Aug 25, 2018 4:36 pm

extensive stakeholder analysis is done in Planning process group, so if I have to choose I will choose C,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
PCS
Posts: 19
Joined: Thu Oct 25, 2018 8:50 am

Re: Question

Postby PCS Thu Nov 08, 2018 11:29 am

If the question was when do you first identify SH or do SH analysis, then i would go with project charter or even the business case. Here its asked " When do you do Stake Holder analysis".
If we choose project charter, it implies we are not doing in other processes ?
From the given options, i choose project management plan, where its mostly done. Although done in other processes not mentioned here.
Manish, can correct me.