SCOPE KNOWLEDGE AREA

Postby VCAB Tue Feb 20, 2018 4:33 pm

You are in the process of subdividing project deliverables and project work into smaller, more manageable parts so the project management team can get a structured vision of what has to be delivered. Which of the following is an output of this process?

(a) Project scope statement
(b) RBS
(c) WBC
(d) OBS
nazrulq
Contributor
Contributor
Posts: 266
Joined: Sun Feb 26, 2017 6:06 am

Re: SCOPE KNOWLEDGE AREA

Postby nazrulq Tue Feb 20, 2018 8:00 pm

Ans: In here the question is talking about breaking work into more manageble in terms of defining scope, I think output of defining scope Project Scope Statement is the correct answer!
Prembalaji
Participant
Participant
Posts: 69
Joined: Wed May 10, 2017 1:38 pm

Re: SCOPE KNOWLEDGE AREA

Postby Prembalaji Thu Mar 01, 2018 8:47 am

create WBS—The process of subdividing project deliverables and project work into smaller, more manageable components.

Answer should be WBS
Cheers,
PJ