EVM - Clarification on a question

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
solidroots
Posts: 6
Joined: Sat Aug 29, 2015 1:16 pm

EVM - Clarification on a question

Postby solidroots Mon Feb 19, 2018 5:54 am

Manjushree is working on a project which has a Budget at Completion (BAC) of INR 8,50,000.00 and is 24 months long. As on date her project is 35% complete, while it was supposed to be 40% complete at present. She has also reported that INR 4,25,000.00 has already been spent on the project. Her project sponsor wants to know the likelihood of the project being able to meet the estimate at completion. Please specify which statement is TRUE?

A. Her sponsor has asked for To-Complete Performance Index (TCPI) which is 0.7.
B. Her sponsor has asked for To-Complete Performance Index (TCPI) which is 1.3.
C. Her sponsor has asked for Estimate at Completion (EAC) which is INR 7,89,286.00
D. Her sponsor has asked for Estimate to Complete which is INR 7,89,286.00
manishpn
Expert
Expert
Posts: 2572
Joined: Sat Jan 04, 2014 3:55 pm

Re: EVM - Clarification on a question

Postby manishpn Mon Feb 19, 2018 4:33 pm

would recommend you to do your own match and we can discuss after that
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
solidroots
Posts: 6
Joined: Sat Aug 29, 2015 1:16 pm

Re: EVM - Clarification on a question

Postby solidroots Tue Feb 20, 2018 3:40 am

As per my understanding and calculations the first option is correct, since estimate at completion is taken to into consideration the formula shall be (BAC-EV)/(EAC-AC) that comes up as 0.7. EAC was calculated using the formula BAC/CPI. However as per the original mocks from where this question is taken up the answer is second. Kindly provide your inputs.