PM Responsibility doubt

Postby msninave Mon Feb 12, 2018 11:11 am

Which of the following represents the project Managers responsibility in regard to change on the project?

A. Prioritize change below execution
B. influence the factors that cause project change
C. ensures all changes are communicated to the CCB
D. Deny change wherever possible

From my point of view PM should deny the changes wherever possible first. Is it correct ?
manishpn
Expert
Expert
Posts: 2412
Joined: Sat Jan 04, 2014 3:55 pm

Re: PM Responsibility doubt

Postby manishpn Mon Feb 12, 2018 10:16 pm

msninave wrote:Which of the following represents the project Managers responsibility in regard to change on the project?

A. Prioritize change below execution
B. influence the factors that cause project change
C. ensures all changes are communicated to the CCB
D. Deny change wherever possible

From my point of view PM should deny the changes wherever possible first. Is it correct ?



is the question correct?
Which of the following represents (or is it does not represents) the project Managers responsibility in regard to change on the project?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
msninave
Posts: 5
Joined: Wed Jan 10, 2018 1:22 pm

Re: PM Responsibility doubt

Postby msninave Tue Feb 13, 2018 1:37 am

Yes. Question is correct. I got this from one of the mock exam and there my answer goes wrong. To clarify my understanding I have posted this to forum.
msninave
Posts: 5
Joined: Wed Jan 10, 2018 1:22 pm

Re: PM Responsibility doubt

Postby msninave Sun Feb 18, 2018 6:52 am

Could you please clarify ?
manishpn
Expert
Expert
Posts: 2412
Joined: Sat Jan 04, 2014 3:55 pm

Re: PM Responsibility doubt

Postby manishpn Sun Feb 18, 2018 1:04 pm

msninave wrote:Which of the following represents the project Managers responsibility in regard to change on the project?

which mock are you referring to and what is the explanation provided?

if I have to choose elimination I would go with option B

A. Prioritize change below execution - Not always true some changes are critical to be prioritized above execution
B. influence the factors that cause project change
C. ensures all changes are communicated to the CCB - Not all changes go to CCB
D. Deny change wherever possible - - maybe true but changes have to be denied with a reasoning and logic

From my point of view PM should deny the changes wherever possible first. Is it correct ?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
msninave
Posts: 5
Joined: Wed Jan 10, 2018 1:22 pm

Re: PM Responsibility doubt

Postby msninave Sun Feb 18, 2018 2:10 pm

Hello Manish,

Thanks for explanation !!!

Thanks and Best Regards
Mangesh