Risk Owner

Posted: Fri Feb 09, 2018 10:45 am
by gargysingh
I which process is owner assigned to a risk?

Identify risk or Plan Risk response?

Re: Risk Owner

Posted: Thu Mar 01, 2018 9:39 am
by Prembalaji
If the Risk Owner is known then the 'RO 'will be assigned during Identify Risk process itself, if not then later.

The key point is Risk Register is an Iterative document and it will be updated throughout the process, as u can notice that updating the Risk Register is an output of all the Risk Management Processes (disguised as Project Document updates ;) )