Risk Owner

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
gargysingh
Posts: 6
Joined: Mon Jan 22, 2018 7:24 am

Risk Owner

Postby gargysingh Fri Feb 09, 2018 10:45 am

I which process is owner assigned to a risk?

Identify risk or Plan Risk response?
Prembalaji
Participant
Participant
Posts: 69
Joined: Wed May 10, 2017 1:38 pm

Re: Risk Owner

Postby Prembalaji Thu Mar 01, 2018 9:39 am

If the Risk Owner is known then the 'RO 'will be assigned during Identify Risk process itself, if not then later.

The key point is Risk Register is an Iterative document and it will be updated throughout the process, as u can notice that updating the Risk Register is an output of all the Risk Management Processes (disguised as Project Document updates ;) )
Cheers,
PJ