Re: During PMP exam do they provide scratch paper?
They Give you 2 A4 size pink color papers and 2 pencils, u cannot carry any of ur own stationary Items inside.
And if run out of the 2 papers they provide u another set of 2 new papers in exchange of previously given papers.
Which means u get to have only 2 papers on ur exam table at any given point of time.
And if run out of the 2 papers they provide u another set of 2 new papers in exchange of previously given papers.
Which means u get to have only 2 papers on ur exam table at any given point of time.
Cheers,
PJ
PJ
- kushalks87
- Contributor
- Posts: 165
- Joined: Sat Aug 19, 2017 10:40 am
Re: During PMP exam do they provide scratch paper?
you will get the papers as prembalaji said however if you run out of the first sheet you will need to create the brain dump again. so for me i never did any brain dump and relied on my memory which did not disappoint me in the final exam
- kushalks87
- Contributor
- Posts: 165
- Joined: Sat Aug 19, 2017 10:40 am
Re: During PMP exam do they provide scratch paper?
yes they do provide calculator but you need to ask beforehand. if you dont ask they assume that you do not require it. 

- deepak_kavathe87
- Posts: 3
- Joined: Fri Sep 22, 2017 6:48 pm
Re: During PMP exam do they provide scratch paper?
Mark is in execution phase of the road construction project in a town which has total duration of 12 months and work effort evenly distributed. 3 months down the line during the execution phase mark realizes that there is a change in local law which demands sound proof fencing of the road passing near the hospitals and School. This task was not foreseen and not included in cost baseline of USD Mn 18. Mark submits a Change request to CCB. While total cost budget for project is USD 25 Mn CCB approves to use USD 2 Mn for additional work from Management reserves to baseline. Ion Mark has been informed that there will be fluctuation in price of cement and timely delivery could also be impacted due to shortage in supply. At the end of 6th month mark present following performance graph to Steering group. Steering Group is keen to complete the project on time and budget and asks Mark about his opinion on how much more will he need to complete the project. Mark answer should be
There is one atypical variance which had resulted in revision of cost baseline as Management reserve of 2Mn was used. However there is also known variances that would occur in future which will impact cost and schedule. In situations where project has to complete on time and variances of both cost and schedule would occur in future, EAC = AC+ ((BAC-EV)/(SPI*CPI))
AC= 11
BAC= 20
SPI= EV/PV= 10/9 = 1.11
CPI= EV/AC = 10/11= 0.9
EAC = 11+ ((20-10)/(1.11*0.9))= 21
ETC = EAC - AC = 10
CAN ANY ONE EXPLAIN ME HOW THIS IS ARRIVED
There is one atypical variance which had resulted in revision of cost baseline as Management reserve of 2Mn was used. However there is also known variances that would occur in future which will impact cost and schedule. In situations where project has to complete on time and variances of both cost and schedule would occur in future, EAC = AC+ ((BAC-EV)/(SPI*CPI))
AC= 11
BAC= 20
SPI= EV/PV= 10/9 = 1.11
CPI= EV/AC = 10/11= 0.9
EAC = 11+ ((20-10)/(1.11*0.9))= 21
ETC = EAC - AC = 10
CAN ANY ONE EXPLAIN ME HOW THIS IS ARRIVED
Re: During PMP exam do they provide scratch paper?
thanks Kushal & balaji.
your inputs are great help..
good that you told i need to ask for calculator beforehand
your inputs are great help..
good that you told i need to ask for calculator beforehand

Re: During PMP exam do they provide scratch paper?
deepak_kavathe87 wrote:Mark is in execution phase of the road construction project in a town which has total duration of 12 months and work effort evenly distributed. 3 months down the line during the execution phase mark realizes that there is a change in local law which demands sound proof fencing of the road passing near the hospitals and School. This task was not foreseen and not included in cost baseline of USD Mn 18. Mark submits a Change request to CCB. While total cost budget for project is USD 25 Mn CCB approves to use USD 2 Mn for additional work from Management reserves to baseline. Ion Mark has been informed that there will be fluctuation in price of cement and timely delivery could also be impacted due to shortage in supply. At the end of 6th month mark present following performance graph to Steering group. Steering Group is keen to complete the project on time and budget and asks Mark about his opinion on how much more will he need to complete the project. Mark answer should be
There is one atypical variance which had resulted in revision of cost baseline as Management reserve of 2Mn was used. However there is also known variances that would occur in future which will impact cost and schedule. In situations where project has to complete on time and variances of both cost and schedule would occur in future, EAC = AC+ ((BAC-EV)/(SPI*CPI))
AC= 11
BAC= 20
SPI= EV/PV= 10/9 = 1.11
CPI= EV/AC = 10/11= 0.9
EAC = 11+ ((20-10)/(1.11*0.9))= 21
ETC = EAC - AC = 10
CAN ANY ONE EXPLAIN ME HOW THIS IS ARRIVED