Responsibilty of Project Funding / Procurement Audit ( Very Important)

Posted: Sat Jan 13, 2018 5:07 pm
by nazrulq
Q. Due to money inflation material cost has increased which led Project Budget to be increased by 15% . Who will approve it ?

1. Project Sponsor
2. Project Manager
3. Functional Manager
4, CCB

Q. Customer is auditing cost, time , scope with vendor which Process the customer is performing.

1. Close Procurement
2. Control Procrement
3. Conduct Procurement
4. Plan Procurement

Re: Responsibilty of Project Funding / Procurement Audit ( Very Important)

Posted: Sun Jan 14, 2018 5:12 am
by ajaynit
1st question's answer:
option 4

1st question's answer:
option 2

Nazrul, whats correct answer?

Re: Responsibilty of Project Funding / Procurement Audit ( Very Important)

Posted: Sun Jan 14, 2018 6:24 pm
by ankurece012
First Question:- Project Sponsor as he will be the one funding project.

Second Question. Conduct Procurement. It looks like quality audit.