Q. Due to money inflation material cost has increased which led Project Budget to be increased by 15% . Who will approve it ?
1. Project Sponsor
2. Project Manager
3. Functional Manager
4, CCB
Q. Customer is auditing cost, time , scope with vendor which Process the customer is performing.
1. Close Procurement
2. Control Procrement
3. Conduct Procurement
4. Plan Procurement
Responsibilty of Project Funding / Procurement Audit ( Very Important)
Re: Responsibilty of Project Funding / Procurement Audit ( Very Important)
1st question's answer:
option 4
1st question's answer:
option 2
Nazrul, whats correct answer?
option 4
1st question's answer:
option 2
Nazrul, whats correct answer?
- ankurece012
- Posts: 7
- Joined: Fri Oct 27, 2017 8:00 pm
Re: Responsibilty of Project Funding / Procurement Audit ( Very Important)
First Question:- Project Sponsor as he will be the one funding project.
Second Question. Conduct Procurement. It looks like quality audit.
Second Question. Conduct Procurement. It looks like quality audit.