Question:
CEO of your company decides to terminate the data storage development project due to technology advancement as he thinks solution already available for same. Software development part of this project was outsourced to a company located in Bangladesh. As the project manager, what is the best thing for you to do next?
A. Initiate administrative closure on the project.
B.Set up a meeting with the CIO and the account manager from software firm in an attempt to save the current project.
C.Initiate contract closeout with software firm.
D.Perform a procurement audit.