Dangerous Stakeholder

Posted: Tue Dec 26, 2017 2:20 am
by nazrulq

Which type of stakeholders could be dangerous for project?


• Stakeholders who has ability to impose their will, need immediate attention, and their involvement is appropriate.
• Stakeholders who has ability to impose their will, does not need immediate attention, and their involvement is appropriate.
• Stakeholders who has ability to impose their will, need immediate attention, and their involvement is not appropriate.
• Stakeholders who has ability to impose their will, does not need immediate attention, and their involvement is not appropriate.

It explains about Salience Model of Stakeholder Analysis. Option 3 could be right choice!

Re: Dangerous Stakeholder

Posted: Tue Dec 26, 2017 7:24 am
by rahul.kanugo
i go with 1 st one

Re: Dangerous Stakeholder

Posted: Tue Dec 26, 2017 8:12 pm
by suresi00
https://pmstudycircle.com/2015/09/salie ... keholders/

This will give u the idea of who is dangerous and who is dominant.

Re: Dangerous Stakeholder

Posted: Wed Dec 27, 2017 12:08 am
by nazrulq
3rd Choice is the right one. See Colour Analysis!

• Stakeholders who has ability to impose their will, need immediate attention, and their involvement is appropriate.
• Stakeholders who has ability to impose their will, does not need immediate attention, and their involvement is appropriate.
• Stakeholders who has ability to impose their will, need immediate attention, and their involvement is not appropriate.
• Stakeholders who has ability to impose their will, does not need immediate attention, and their involvement is not appropriate.

Red -Red is Dangerous! :oops:
Green- Green is suppotive or leading.

Hopefully it Clarifies!