Discretionary dependencies

Posted: Fri Dec 22, 2017 2:35 pm
by Prembalaji
How can a Project Manager use his knowledge of Discretionary dependencies on the Project?

1.It helps to determine the optional tasks in a project
2.Discretionary dependencies can be relaxed to fast track a project
3.Discretionary dependencies can be relaxed to crash a project
4.Discretionary dependencies help determine the optional team members on a project

Re: Discretionary dependencies

Posted: Mon Dec 25, 2017 6:39 am
by manishpn
try to make an attempt

Re: Discretionary dependencies

Posted: Mon Dec 25, 2017 7:31 am
by ajaynit
I feel it should be :


2.Discretionary dependencies can be relaxed to fast track a project

Re: Discretionary dependencies

Posted: Tue Dec 26, 2017 2:27 am
by nazrulq
Option 2 is the right choice .PMBOK 5 Page-158 .1st paragraph, last three lines!

Re: Discretionary dependencies

Posted: Tue Dec 26, 2017 7:21 am
by rahul.kanugo
answer 2 as in fast tracking sucessor job can be done along predecessr activity ......in discretionary process can be relaxed.