If there are unresolved claims which are subjected to litigation which might take prolonged time to settle.
Can we close the project as of now and update docs once the litigation are settled ?
Prembalaji
Participant
Participant
Posts: 69
Joined: Wed May 10, 2017 1:38 pm

Re: Closing phase

Postby Prembalaji Tue Dec 19, 2017 3:23 am

Yes, Litigations and Unresolved claims that end up in courts, should be settled after closing the Procurement.

Procurement closure need not wait for Litigations to get settled.

Saket's video on Procurement closure explains this in details
Cheers,
PJ