Decomposition

Postby nazrulq Sat Dec 09, 2017 9:19 pm

Q. Decomposition is a must to create activity of the project . Which of the following does n't say much about decomposition:

1. Until it can n' t be realistically estimated.
2. Activities can not be decomposed.
3.Until meaningful conclusion.
4. Can not decomposed more that 5 levels.

Correct Answer is option4 .

Can somebody explain why not 2!

Thanks.