Mock Exam Question#2 - Reasoning

Postby Prembalaji Fri Dec 01, 2017 8:57 am

Dear Team , Please share your answers and your reasons for the attached question , I'll share the answers after a few replies
Attachments
Q3.jpg
Q3.jpg (113.25 KiB) Viewed 920 times
Cheers,
PJ
rahul.kanugo
Participant
Participant
Posts: 67
Joined: Tue May 17, 2016 4:42 pm

Re: Mock Exam Question#2 - Reasoning

Postby rahul.kanugo Fri Dec 01, 2017 1:07 pm

i think 1 will be appropriate answer where PM is having hope to get exceeded money under organisation procedures
suresi00
Contributor
Contributor
Posts: 150
Joined: Mon Nov 20, 2017 4:05 pm

Re: Mock Exam Question#2 - Reasoning

Postby suresi00 Fri Dec 01, 2017 2:01 pm

If I dissect I see

1. Project budget exceeded
2. So no more management reserve



What do a project manager do if the management reserve is also used up? I And he didn't ask any permission and granted it.
Before he proceed with what to do , he needs to discuss this with stakeholder and see the procedure to be followed as Project budget is exceeded.

I also feel contingency can be used only planned once with proper trigger.
pradeepbhatt13
Posts: 3
Joined: Sat Mar 18, 2017 7:30 am

Re: Mock Exam Question#2 - Reasoning

Postby pradeepbhatt13 Fri Dec 01, 2017 6:04 pm

Can you please let me know the source of this mock exam?
Prembalaji
Participant
Participant
Posts: 69
Joined: Wed May 10, 2017 1:38 pm

Re: Mock Exam Question#2 - Reasoning

Postby Prembalaji Sat Dec 02, 2017 1:56 am

Correct Answer is : A
Cheers,
PJ