Postby nazrulq Fri Dec 01, 2017 3:20 am

Correct Answer D.




Justification

Issue log is an output of Manage Stakeholder Engagement. Since New Stakeholder is added in the Project

Stakeholder Management Plan to be updated. List of Stakeholder which is Stakeholder register is needed to be

revised with the new addition. New Stakeholder could be resistant which could increase the project risk.

Risk Register in this regards needs to be updated.

So only option is Issue log. But it could be updated as project document uodates incase of any new conflict.

As nothing is mentioned in the question about the stakeholder issues , so option D could be best choice.