CSM Forum Banner

Project Report And Project Record

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
shaibajit
Beginner
Beginner
Posts: 26
Joined: Tue Aug 22, 2017 3:38 pm

Project Report And Project Record

Postby shaibajit Tue Nov 21, 2017 8:21 pm

Project file, Project records, Project closure docs, Historical info

What is the relation among above docs? I know they are part of OPA. But are they subsets of each other?
suresi00
Contributor
Contributor
Posts: 116
Joined: Mon Nov 20, 2017 4:05 pm

Re: Project Report And Project Record

Postby suresi00 Tue Nov 21, 2017 10:52 pm

They are all part of OPA.

They are not really subset of each other :

Project files: Documentation from activities :{project management plan, scope,cost etc. these are from project activities}
Project closure: will describe why the project is closed. customer acceptance--- this is mainly the documents which needs to finalized for closure or kill point
Historical document: lessons learned from the project what went well how did u take care of an issue . how did u manage the stakeholder who was creating issues in the project.

To add to more
Project report -Project status report
Project records: what are the documents created from the activities like meetings, memo etc. This is may in line with project files.

Refer PMBOK -104 and also under stakeholder
shaibajit
Beginner
Beginner
Posts: 26
Joined: Tue Aug 22, 2017 3:38 pm

Re: Project Report And Project Record

Postby shaibajit Wed Nov 22, 2017 1:48 pm

Thank you!!!