i have marked answer as C..............please suggest as correct answer is D
Attachments
procurement2.PNG
procurement2.PNG (244.89 KiB) Viewed 91 times
manishpn
Expert
Expert
Posts: 2328
Joined: Sat Jan 04, 2014 3:55 pm

Re: procurement Q/A 2

Postby manishpn Mon Nov 13, 2017 9:32 pm

the wording of this question is not good , it creates confusion ,

Of course if contract is T and M that will be biggest concern for the PM,
the contract type is not defined well in the process, so option C cant be true if its FP project where scope and cost are agreed in advance,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/