Output of Perform Integrated Change Control Process

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
aarkay
Posts: 10
Joined: Mon Jun 06, 2016 5:41 pm

Output of Perform Integrated Change Control Process

Postby aarkay Sun Nov 12, 2017 9:24 pm

Hi,

Referring to Figure XI-1 in PMBOK, page 467: "Refined Data Model"

Output of "Perform Integrated Change Control" Process is shown as change requests which is going in to "Develop Project Management Plan".

I see in the "Perform Integrated Change Control Process" explanation (page 94 of PMBOK) that "Approved Change requests" are O/P of this process which trigger updates to Project Management plan, and that "change requests" are input to this process.

Is there a mistake in the "Refined Data Model" flow chart or am I missing something?
Please advise.

Thank you.
Rohini.
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Output of Perform Integrated Change Control Process

Postby manishpn Mon Nov 13, 2017 8:55 pm

yes its mistake/overlook good catch
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
aarkay
Posts: 10
Joined: Mon Jun 06, 2016 5:41 pm

Re: Output of Perform Integrated Change Control Process

Postby aarkay Tue Nov 14, 2017 3:14 pm

Thanks Manish.