Change Control

Posted: Thu Oct 19, 2017 4:02 am
by nazrulq
A regularly scheduled inspection of the manufacturing line is completed and has noted that a key piece of machinery is showing signs of wear and damage much earlier than expected. A change request has been submitted to be reviewed by the Change Control Board to interrupt product manufacturing in order to replace the damaged parts of machinery. This unscheduled repair will take the entire manufacturing line down for two weeks. Without the repair the machinery could fail and cause more extensive damage resulting in a much longer and more expensive work stoppage. The CCB approves the change request and schedules the repair work to be completed as soon as possible. This is best described as:

a. Corrective action
b. Defect repair
c. Preventive action
d. Monitoring and Controlling Project Work

Correct Answer : Option C

Can Saket or Manish Justify please!

Re: Change Control

Posted: Thu Oct 19, 2017 4:50 pm
by manishpn
this one a thin line between defect repair and preventive.
'showing signs of wear and damage much earlier than expected' 'order to replace the damaged parts of machinery'

the above information makes me more inclined towards defect repair as an option

Re: Change Control

Posted: Fri Oct 20, 2017 5:08 am
by rahul.kanugo
a. Corrective action:-Corrective action is after prevention. Prevention is already take as machine wear and tear happened before expected time.
b. Defect repair:- defect of product not produced yet thus ,it is not valid.
c. Preventive action:- Wear and tear is identified much earlier than expectation,thus there might be preventive action taken before.


Experts suggestion required.
Thanks

Re: Change Control

Posted: Fri Oct 20, 2017 5:59 am
by manishpn
rahul.kanugo wrote:a. Corrective action:-Corrective action is after prevention. Prevention is already take as machine wear and tear happened before expected time.
b. Defect repair:- defect of product not produced yet thus ,it is not valid.
'order to replace the damaged parts of machinery', when a part of machine is damaged it may be called as defect, although it is not a defect in deliverable, thats the reason I said its difficult to decide.
c. Preventive action:- Wear and tear is identified much earlier than expectation,thus there might be preventive action taken before.


Experts suggestion required.
Thanks

Re: Change Control

Posted: Fri Oct 20, 2017 4:01 pm
by pmp_learner
So whats the correct answer? Defect repair or Preventive action?

What is the source of the question Nazrulq if you please don't mind sharing.. also if you can please share the explanation given.

Thanks
Kavita

Re: Change Control

Posted: Sat Oct 21, 2017 7:36 pm
by manishpn
If i had to choose I will choose option C since the defect is not in deliverable, however as I said its difficult to choose

Re: Change Control

Posted: Sat Oct 21, 2017 9:06 pm
by pmp_learner
Thanks Manish

Re: Change Control

Posted: Mon Oct 23, 2017 9:05 pm
by nazrulq
Those are really confused questions! I hope in real PMP question will be straight forward!
Thanks for the participation!

Re: Change Control

Posted: Tue Oct 24, 2017 4:13 pm
by nazrulq
The answer option should be preventive action and defect repair. That would be the best answer. Unfortunately, those questions make people fail in the exam! As mostly fail for 10 to 20 questions . That does n't mean your knowledge is limited. I think PMI should take out confused questions from their data base in regular basis!