Perform integrated Change Control

Posted: Wed Oct 18, 2017 6:19 am
by nazrulq
Q. Perform Integrated Change Control Process is conducted from project inception through completion and is ultimately
the responsibility of the:

Answer:

1. Project Sponsor
2. Project manager
3. Project Stakeholders
4. None of the above.

Q. Who is Responsible for Change Management

1. Project Manager
2. Team lead
3. Functional manager
4. Project Manager or Project Sponsor.

Re: Perform integrated Change Control

Posted: Wed Oct 18, 2017 2:01 pm
by saket
In general (untill question reflect something special) Project Manager is responsible for ensuring all 47 Processes of PMBOK performed well. Project Integration Management knowledge area is many time considered the primary role of PM since PM need to ensure everything remains integrated to achieve the project objectives. So PM is definitely responsible for Integrated Change Management.

Re: Perform integrated Change Control

Posted: Thu Oct 19, 2017 3:58 am
by nazrulq
Thanks Saket.


Project Manager is Responsible for All processes (47) from inception to completion,
Ref : PMBOK 5 Page -96 ; Ist Paragraph.

Change Management such as change request either to be approved or rejected is Project Manager or Project sponsor is ultimately responsible.
PMBOK -5 ,page -96 3rd paragraph.