Stakeholder Analysis query.

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
nirajsys@gmail.com
Participant
Participant
Posts: 72
Joined: Tue Jul 11, 2017 9:28 am

Stakeholder Analysis query.

Postby nirajsys@gmail.com Mon Oct 02, 2017 7:41 am

The Finance head of your company plays a vital role in approving funding for your project, but since this project is primarily belong to sales group, finance head is not involved in project demo , which of the following stakeholder management strategy would be most appropriate for finance head ?

A.Keep Satisfied

B.Manage Closely

C.Monitor

D.Keep Informed


answer given is option A.

But finance head is also in the top management and needs to be monitored closely.
Hence,would option B not be the most appropriate choice?
kushalks87
Contributor
Contributor
Posts: 102
Joined: Sat Aug 19, 2017 10:40 am

Re: Stakeholder Analysis query.

Postby kushalks87 Mon Oct 02, 2017 8:35 am

yes even i would answer B as well. Wouldnt this come under low power high interest category of stakeholder?
nazrulq
Contributor
Contributor
Posts: 235
Joined: Sun Feb 26, 2017 6:06 am

Re: Stakeholder Analysis query.

Postby nazrulq Tue Oct 03, 2017 2:23 am

Whatever his role is in different stages of the project, he is the ultimate approver of project funding. He has to be managed by PM very closely.

Option B is the right choice in my opinion!