Workaround is the negative risk for which the project is not planned for. It is managed by contingency reserve.
My question all risks are in response to plan risk response ( Fallback plan, residual risk, secondary risk) but why
workaround is done in control risk process why not planning as risk response. Is that only not for planned early!

Can somebody explain!

Thanks.

Re: Workaround

Posted: Sun Sep 24, 2017 11:21 am
by manishpn
I have explained this before many times,

Workaround are NOT PLANNED, its used if your initial response is not effective enough.

There workarounds are not planned in planning stage

Re: Workaround

Posted: Thu Oct 05, 2017 5:36 pm
by nazrulq
As there is no execution phase for the Risk Management in PMBOK5 it should be in Monitor and control. But According to PMBOK6 it would be in execution phase! We are safe till March 26,2018! :D :D