Postby Rajkumar Thu Sep 21, 2017 7:31 am

Performance review meetings are held to assess schedule activity and work packages over-running or under-running the budget and to determine any estimated funds needed to complete work in progress. Typically, if EV is being used, all but which of the following information is determined?

a. Variance analysis
b. Trend analysis
c. Time reporting systems
d. Earned value performance

Which option is correct? Please answer and would be great if you can provide the rationale as well.

Thanks,
Raj
nirajsys@gmail.com
Participant
Participant
Posts: 74
Joined: Tue Jul 11, 2017 9:28 am

Re: Question regarding EV

Postby nirajsys@gmail.com Fri Sep 22, 2017 2:19 am

I feel option c should be correct.

Refer pg.222 of PMBOK.

All others are covered as part of performance review.The question is asking "all but which".
manishpn
Expert
Expert
Posts: 2333
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question regarding EV

Postby manishpn Fri Sep 22, 2017 5:53 am

Yes i Agree this is fairly simple question, not sure if you got confused due to 'all but which'
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 255
Joined: Sun Feb 26, 2017 6:06 am

Re: Question regarding EV

Postby nazrulq Sun Sep 24, 2017 4:25 am

That is totally correct! Straight forward.
kushalks87
Contributor
Contributor
Posts: 133
Joined: Sat Aug 19, 2017 10:40 am

Re: Question regarding EV

Postby kushalks87 Sun Sep 24, 2017 1:55 pm

answer should be c