Cost management question

Postby rahul.kanugo Mon Sep 18, 2017 1:25 pm

Please justify answer with calculation. Actually i did't get it.
Attachments
cost 1.PNG
cost 1.PNG (129.87 KiB) Viewed 135 times
manishpn
Expert
Expert
Posts: 2157
Joined: Sat Jan 04, 2014 3:55 pm

Re: Cost management question

Postby manishpn Mon Sep 18, 2017 5:14 pm

hourly rate 1400
Fringe benefit 420
wage+fringe benefit 1820
overhead cost 1512
total hourly wage 2912
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
rahul.kanugo
Beginner
Beginner
Posts: 30
Joined: Tue May 17, 2016 4:42 pm

Re: Cost management question

Postby rahul.kanugo Tue Sep 19, 2017 12:55 pm

Hi expert i am still not clear especially over head part .....

hourly rate 1400
Fringe benefit 420(30% of wage)
wage+fringe benefit 1820(sum of wage and fridge)
overhead cost 1512(as per me is should be 60% of 1820= 1092)
total hourly wage 2912

:(

Please eleborate

Thaks
manishpn
Expert
Expert
Posts: 2157
Joined: Sat Jan 04, 2014 3:55 pm

Re: Cost management question

Postby manishpn Tue Sep 19, 2017 6:50 pm

its 60% of wages + Fringe Benifits
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
rahul.kanugo
Beginner
Beginner
Posts: 30
Joined: Tue May 17, 2016 4:42 pm

Re: Cost management question

Postby rahul.kanugo Wed Sep 20, 2017 12:40 pm

thanks ,,,question itself does not give clear information ,,i suppose