What to do when quality review finds quality issues?

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
seema.sonkiya
Expert
Expert
Posts: 1772
Joined: Fri Jul 11, 2014 11:57 am

What to do when quality review finds quality issues?

Postby seema.sonkiya Mon Sep 18, 2017 5:49 am

Request for participation in the following question:

Organization ABC is globally renowned Automobile manufacturer. They initiated a joint project launched in parallel with organization XYZ which specializes in high-tech engines.

A contract is signed between two organizations. Quality Management Plan includes Pareto diagram, Checksheets, and Ishikawa diagrams primarily. To ensure compliance with stringent quality standards, you as a project manager need to collaborate various business units.

A joint meeting of the project team from both organizations reviews quality findings every week. Since last few meeting, quality issues for strength and durability of the product are on rising, thus you:

• Created a graph of all quality issues over last few months and
• Doing brainstorming with the project team to help address quality issues.

What should you focus on in above activities? Also, note that Steering group is scheduled in 2 weeks and project reporting to various stakeholders has to happen in this week?


A Brainstorm the findings and identify best possible way to report the data to different stakeholders to make them aware of quality issues

B Check the result of quality measures study them, measure effectiveness and define how you can improve the quality plan, share this information with stakeholders on how you plan to improve quality

C. Perform trend analysis on quality issues, anticipate possible future behavior and desired outcome and share the information in readable format to various stakeholders before sharing with Steering group

D. Analyse if any preventive action can be taken, calculate the cost of such conformance and verify if the signed contract has any provision for handling such costs.

Which option is correct?
pmp_learner
Participant
Participant
Posts: 82
Joined: Fri Dec 02, 2016 10:18 pm

Re: What to do when quality review finds quality issues?

Postby pmp_learner Wed Oct 25, 2017 12:08 am

I think D ..
per description looks like Increase in Quality issues has been observed.. By creating graph, you are doing trend analysis , team is trying to find the options to address the quality issues..
Option A, B and C not correct choice because :
Option A talks about presenting the data, Option B talks about improving the quality plan, which is a preventive action, but as issues have already occurred, it needs corrective action. Option C is forecast and again how to present this information. Thats why I think D is the best choice as PM you should try to find if preventive actions can be taken to prevent these issues in future, assess the cost to fix the issues and verify if the signed contract has any provision for handling such costs...

Seema/Manish : Could you please share the correct answer with explanation.

Thanks
Kavita
rahul.kanugo
Beginner
Beginner
Posts: 40
Joined: Tue May 17, 2016 4:42 pm

Re: What to do when quality review finds quality issues?

Postby rahul.kanugo Wed Oct 25, 2017 5:27 am

A Brainstorm the findings and identify best possible way to report the data to different stakeholders to make them aware of quality issues....This is more focused towards presenting report ,

B Check the result of quality measures study them, measure effectiveness and define how you can improve the quality plan, share this information with stakeholders on how you plan to improve quality. rCorrect answe ..... as there mght be requirement in Quality improvement plan. May be previous PLAN does not fits quality Standards

C. Perform trend analysis on quality issues, anticipate possible future behavior and desired outcome and share the information in readable format to various stakeholders before sharing with Steering group................Corrective action is required rather producing assumption on future behaviour

D. Analyse if any preventive action can be taken, calculate the cost of such conformance and verify if the signed contract has any provision for handling such costs................It talks about preventive maintance, which is not valid at this time.
kushalks87
Contributor
Contributor
Posts: 107
Joined: Sat Aug 19, 2017 10:40 am

Re: What to do when quality review finds quality issues?

Postby kushalks87 Wed Oct 25, 2017 10:20 am

I would go with D. The reason is that scenario states that quality problems are on rise. PM's primary responsibility is to ensure that he proactively looks for issues and ensure that quality problems dont come up in UAT