Procurement Management Influence

Postby nazrulq Fri Sep 15, 2017 12:17 am

Decisions made in developing the procurement management plan may have least influence on ……..

1.Project Schedule

2.Project Budget

3.Project Human Resource Need

4.Risk Management Plan

Correct Answer:3

Explanation given are not much satisfactory can Manish elaborate please!
nirajsys@gmail.com
Participant
Participant
Posts: 72
Joined: Tue Jul 11, 2017 9:28 am

Re: Procurement Management Influence

Postby nirajsys@gmail.com Fri Sep 15, 2017 2:44 am

Procurement management plan would mainly include risk management issues, constraint & assumptions and handling long lead times impacting schedule,contract types impacting budget.

Moreover focus of procurement management plan is more on enabling make or buy decisions through clear & concise procurement SOW.

HR management seems to be the least impactful amongst all choices.