Q. Project Manager along with team member discuss about the fast tracking of the project schedule. To fast track which of the following statement are true:

1. Project has extra money in contingency reserve.
2. The project has high risk.
3. Activities have preferential dependencies.
4. Add resources to the activities to fast track.
nirajsys@gmail.com
Participant
Participant
Posts: 72
Joined: Tue Jul 11, 2017 9:28 am

Re: Fast Tracking

Postby nirajsys@gmail.com Thu Sep 14, 2017 8:47 am

Option 3 seems apt.

Option 2 is not recommend as high risk cud be caused through rework in fast tracking.

Option 1 is related to identified risk handling.

Option 4 is related to crashing.

Pls advise.
maverick
Posts: 5
Joined: Wed Aug 02, 2017 11:41 am

Re: Fast Tracking

Postby maverick Mon Sep 18, 2017 9:13 am

Fast Tracking essentially relate to having a parallel arrangement to complete a task. To me, option 3 makes sense as using a preferential logic or soft or preferred logic would facilitate fast tracking. Hence #3. Activities have preferential dependencies should be the choice.