Change Request!

Posted: Mon Sep 11, 2017 5:29 pm
by nazrulq
If changes are approved by CCB but rejected by sponsor, in that case baselines is needed to be updated! As there is a rejection. No need for updation. CCB approved does n't mean baselines need to be updates! CCB's approvals for changes are not final! :o
I think, Izenbridge Webinar missed that point ! Now a days questions are really confusing!

Can Manish or Saket Clarify Please!

Re: Change Request!

Posted: Mon Sep 11, 2017 8:14 pm
by manishpn
nazrulq wrote:If changes are approved by CCB but rejected by sponsor,
there is usually not 2 levels of approval for CRs
usually sponsor is part of CCB
if CCB approves that usually change is considered as approved
Of course exception can be if mentioned in Project management plan thta after CCB the sponsor also needs to approve the change


in that case baselines is needed to be updated! As there is a rejection. No need for updation. CCB approved does n't mean baselines need to be updates! CCB's approvals for changes are not final! :o
I think, Izenbridge Webinar missed that point ! Now a days questions are really confusing!

Can Manish or Saket Clarify Please!

Re: Change Request!

Posted: Wed Sep 13, 2017 3:13 pm
by komal
Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.

Re: Change Request!

Posted: Wed Sep 13, 2017 3:14 pm
by komal
Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.

Re: Change Request!

Posted: Wed Sep 13, 2017 7:23 pm
by manishpn
komal wrote:Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.

correct hwever unless mentioned explicitly in contract you should consider CCB as final authority for changes approval

Re: Change Request!

Posted: Fri Oct 06, 2017 5:39 pm
by nazrulq
Thanks Manish for clarity!