Scope Management Mockups

Postby komal Sun Sep 10, 2017 1:32 pm

You are working on a software development project. The sponsor wants to make a change to the Scope after it has been baseline. You want to know the procedure that how to manage these changes. What is the BEST place to look for this information?


WBS

Scope management plan

Change request template

Business Case
nirajsys@gmail.com
Participant
Participant
Posts: 72
Joined: Tue Jul 11, 2017 9:28 am

Re: Scope Management Mockups

Postby nirajsys@gmail.com Sun Sep 10, 2017 4:46 pm

The question talks about to know the procedure to make changes,hence options c & d are ruled out.

Option A is rule out as change is mentioned after baseline.scope baseline contains WBS.

Moreover,scope management plan contains procedure to handle CR,wch in turn is connected to integrated change control.

Option b is the correct choice.