Contingency reserve tricky question.

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
nirajsys@gmail.com
Participant
Participant
Posts: 58
Joined: Tue Jul 11, 2017 9:28 am

Contingency reserve tricky question.

Postby nirajsys@gmail.com Sun Sep 10, 2017 9:34 am

Hello Group members,

Need advise on the question attached in the pic.

What's should be the correct choice?
Attachments
image_23fcf2e7-fee1-4b45-b223-0949cc8be3b620170910_145804.jpg
image_23fcf2e7-fee1-4b45-b223-0949cc8be3b620170910_145804.jpg (25.38 KiB) Viewed 256 times
manishpn
Expert
Expert
Posts: 2131
Joined: Sat Jan 04, 2014 3:55 pm

Re: Contingency reserve tricky question.

Postby manishpn Sun Sep 10, 2017 10:12 am

good question would let other attempt for a good discussion
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nirajsys@gmail.com
Participant
Participant
Posts: 58
Joined: Tue Jul 11, 2017 9:28 am

Re: Contingency reserve tricky question.

Postby nirajsys@gmail.com Sun Sep 10, 2017 4:38 pm

Contingency reserve are derived as a percentage of residual risk of overall project.hence I feel option c seems to be apt.

In the question,risk A has not occurred.So we could keep the reserve for future residual risks.

Pls advise.
kushalks87
Beginner
Beginner
Posts: 37
Joined: Sat Aug 19, 2017 10:40 am

Re: Contingency reserve tricky question.

Postby kushalks87 Sun Sep 10, 2017 6:39 pm

keep it for residual risks as these risks are the one which remain which we could not plan a risk response on
nazrulq
Contributor
Contributor
Posts: 217
Joined: Sun Feb 26, 2017 6:06 am

Re: Contingency reserve tricky question.

Postby nazrulq Mon Sep 11, 2017 5:56 am

Let me try to give the answer in elaborate approach. Let's discuss what is a residual risk and secondary risk.
Residual Risks are the risks which remain after risk response. Now what is secondary risk! Secondary risk (Unknown is the risk after implementing risk response. These could be new risks. Those are not remaining risk.
On the question $8000 has been kept for risk A as a form of residual risk inform of the contingency reserve. Risk did n't happen.
There are probably time when they anticipate those risk. That time has been passed so the anticipated risk informs of residual risk did not happen but it does not mean its not going to happen or zero probability.
I would keep the fund as the residual risk rather transfer it to management reserve and tackle it when it happens (unknown- unknown). But in terms of cost saving, it could be transferred as management reserve and deal with unknown -unknown. Little confusing since the question is emphasizing on risks I would go for Residual Risk (Oprtion C).
manishpn
Expert
Expert
Posts: 2131
Joined: Sat Jan 04, 2014 3:55 pm

Re: Contingency reserve tricky question.

Postby manishpn Mon Sep 11, 2017 8:22 pm

nirajsys@gmail.com wrote:Hello Group members,

Need advise on the question attached in the pic.

What's should be the correct choice?


Correct option should be B

During the project as part of control risk process, PM does reserve analysis. this is to find out if contingency reserves are adequate it also deals with releasing contingency risk amounts if risk is not longer valid i.e. risk has expired, in this process PM also validates is contingency buffer is adequate at the time of evaluation
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nirajsys@gmail.com
Participant
Participant
Posts: 58
Joined: Tue Jul 11, 2017 9:28 am

Re: Contingency reserve tricky question.

Postby nirajsys@gmail.com Tue Sep 12, 2017 4:15 am

Agreed Manish.

Found it...Pg.225 of PMBOK under Reserve Analysis heading... clarifies that if a contingency buffer is not used ,due to risk not occuring,it should be removed from project budget.

Thanks.
nazrulq
Contributor
Contributor
Posts: 217
Joined: Sun Feb 26, 2017 6:06 am

Re: Contingency reserve tricky question.

Postby nazrulq Tue Sep 12, 2017 4:40 am

Thanks ! Really interesting question!
pmp_learner
Participant
Participant
Posts: 79
Joined: Fri Dec 02, 2016 10:18 pm

Re: Contingency reserve tricky question.

Postby pmp_learner Tue Sep 12, 2017 10:11 pm

Interesting question.. if it was not discussed here and would have appeared in exam , I would have confidently gone for Option C :( :( :( ..
Thanks for the explanation Manish and Neeraj for PMBOK reference.. Just another question out of curiosity.. When PM removes this from Contingency Reserve, where would that money go? I assume PM will not move towards Management reserve (MR) as MR is not managed by PM.

Thanks
Kavita



manishpn wrote:
nirajsys@gmail.com wrote:Hello Group members,

Need advise on the question attached in the pic.

What's should be the correct choice?


Correct option should be B

During the project as part of control risk process, PM does reserve analysis. this is to find out if contingency reserves are adequate it also deals with releasing contingency risk amounts if risk is not longer valid i.e. risk has expired, in this process PM also validates is contingency buffer is adequate at the time of evaluation
komal
Participant
Participant
Posts: 55
Joined: Wed May 31, 2017 4:34 pm

Re: Contingency reserve tricky question.

Postby komal Wed Sep 13, 2017 2:47 pm

I have not seen any such definition in PMBOK if contingency reserved is not used for risk, eliminate it. Please share screen shot .
manishpn
Expert
Expert
Posts: 2131
Joined: Sat Jan 04, 2014 3:55 pm

Re: Contingency reserve tricky question.

Postby manishpn Wed Sep 13, 2017 8:42 pm

you will not find every question in exam which is covered by PMBOK.

You can refer to risk practice guide from PMI if you really want to dig into details, , even there this is no straight forward statement but one has to understand and derive from the practice guide content
Last edited by manishpn on Wed Sep 13, 2017 8:45 pm, edited 1 time in total.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
manishpn
Expert
Expert
Posts: 2131
Joined: Sat Jan 04, 2014 3:55 pm

Re: Contingency reserve tricky question.

Postby manishpn Wed Sep 13, 2017 8:43 pm

pmp_learner wrote:Interesting question.. if it was not discussed here and would have appeared in exam , I would have confidently gone for Option C :( :( :( ..
Thanks for the explanation Manish and Neeraj for PMBOK reference.. Just another question out of curiosity.. When PM removes this from Contingency Reserve, where would that money go?
Money would go back to sponsor and he/she can use it for need of other projects
I assume PM will not move towards Management reserve (MR) as MR is not managed by PM.

Thanks
Kavita



manishpn wrote:
nirajsys@gmail.com wrote:Hello Group members,

Need advise on the question attached in the pic.

What's should be the correct choice?


Correct option should be B

During the project as part of control risk process, PM does reserve analysis. this is to find out if contingency reserves are adequate it also deals with releasing contingency risk amounts if risk is not longer valid i.e. risk has expired, in this process PM also validates is contingency buffer is adequate at the time of evaluation
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/