Hi Experts seeking your advice on time menagement Q/A
Attachments
time management 3.PNG
time management 3.PNG (53.32 KiB) Viewed 175 times
time management 2.PNG
time management 2.PNG (8.22 KiB) Viewed 175 times
time management 1.PNG
time management 1.PNG (15.15 KiB) Viewed 175 times
manishpn
Expert
Expert
Posts: 2199
Joined: Sat Jan 04, 2014 3:55 pm

Re: time menagement Q/A

Postby manishpn Wed Sep 06, 2017 4:54 pm

kindly post 1 question per thread.

for SND calculations we always recommend that you do you own calculation on a paper , take picture and upload it here this is the best way to learn
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 235
Joined: Sun Feb 26, 2017 6:06 am

Re: time menagement Q/A

Postby nazrulq Wed Sep 06, 2017 8:31 pm

Q 13. The answer I think, should be lag time.

Total Float : The amount of time that a schedule activity can be delayed or extended from its early start without delaying project finish date or violating schedule constraint.

Lag : The amount of time whereby successor activity is required to be delayed with respect to predecessor activity.

Q12. Minimum Milestone between A and B is 37