Conduct Procurement

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
nazrulq
Contributor
Contributor
Posts: 270
Joined: Sun Feb 26, 2017 6:06 am
Location: Canada

Conduct Procurement

Postby nazrulq Mon Aug 28, 2017 4:10 am

Question :Larry is the project manager and working with procurement department of his organization to do procurement for his project. Procurement department said these are usual commodities and same has been procured many time. Also as this has been procured multiple times, generally they receive response from 4-5 vendors for this procurement. To everyone’s surprise, almost 10-15 vendors responded and two of the bids are evidently lesser than independent estimate Larry has created. What can be the best explanation for lower bid in this scenario?

1.Price for the commodity in current market changed due to change in demand/supply for it

2.Procurement SOW created by buyer was not clear enough for seller to make out the requirement

3.Procurement SOW created by buyer was clear but seller understood it incorrectly resulting lower bids

4. Bid document supplied by seller is having formula mistake resulting in lower bid

Correct Answer : Option 1

I initially thought Option 2.

But the reasons are those commodities are procured many times. So scope is clear enough. Market Price has changed may be reduced so that more vendors have submitted bid!

The Question is not clear enough. For some question Option 2 is correct.

Can Manish explain the difference of choosing options specifically which one is the closer one by elimination!
manishpn
Expert
Expert
Posts: 2553
Joined: Sat Jan 04, 2014 3:55 pm

Re: Conduct Procurement

Postby manishpn Mon Aug 28, 2017 10:07 am

nazrulq wrote:Question :Larry is the project manager and working with procurement department of his organization to do procurement for his project. Procurement department said these are usual commodities and same has been procured many time. Also as this has been procured multiple times, generally they receive response from 4-5 vendors for this procurement. To everyone’s surprise, almost 10-15 vendors responded and two of the bids are evidently lesser than independent estimate Larry has created. What can be the best explanation for lower bid in this scenario?

1.Price for the commodity in current market changed due to change in demand/supply for it

2.Procurement SOW created by buyer was not clear enough for seller to make out the requirement

3.Procurement SOW created by buyer was clear but seller understood it incorrectly resulting lower bids

4. Bid document supplied by seller is having formula mistake resulting in lower bid

Correct Answer : Option 1

I initially thought Option 2.

But the reasons are those commodities are procured many times. So scope is clear enough. Market Price has changed may be reduced so that more vendors have submitted bid!

The Question is not clear enough. For some question Option 2 is correct.

Can Manish explain the difference of choosing options specifically which one is the closer one by elimination!


Its easy to attack this question it if one has done a lot of procurement in real. the best way to deal with this is through elimination.
'Procurement department said these are usual commodities and same has been procured many time.'

when it comes to procuring standard commodities then you don't really need to describe a lot of requirements and neither there is chance of misunderstanding the same so option #2 and #3 are ruled out.
and there is no need to detailed formula etc as its standard commodity , at the most you need multiplication formula to calculate total price from per commodity price.
Hence option #4 is also ruled out.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
anand.sutar
Posts: 7
Joined: Fri Apr 27, 2018 10:10 am
Location: Pune

Re: Conduct Procurement

Postby anand.sutar Wed Oct 03, 2018 4:11 am

Lesson learned is,
This is more than one minute question, and need to understand the situation and as per situation associate factors to whom we suppose to deal.

Situation is regular order, so regular order it is a repetitive work, so MOSTLY no one will do the market research, since it’s may be already done by organization procurement department, and may be organization has put some bracket/ range of it.
E.g like ordering stationary. So our Organization and Larry are correct with procurement cost.

Now consider the seller part, they are continuous of supplying this items and definitely know the exact cost.

Might be old vendors will raise same quote because they know buyer is past history of buying at this rate. but here it’s mentioned that new quote also received which was less.

This scenario shows Buyer is correct, seller is correct at his procedure but new seller quoted low, due to change in demand / supply with latest price.

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 11 guests